Stage 3
2024-07-17

Wedge Rd. Skye construction continues to progress.
Stage 3 is now Titled.
If you have any queries regarding your block at Wedge Rd, we recommend speaking with your conveyancer in the first instance. If you would like to reach out to us, please contact us on 0473 630 484 or email us at hello@wedgerd.com.au
March 2025:
- Construction is complete and stage 3 is now Titled.
February 2025:
- Civil construction works are now complete.
- Authority inspections have been completed, and final compliance approvals are anticipated shortly.
- Titles are expected March 2025.
November 2024:
- Civil works including electrical and communications installation is underway and due to complete this month.
- Footpath pour is due to complete this month.
- Authority inspections and final compliance approvals are due to begin shortly.
October 2024:
- Electrical & communications install underway, nearing completion.
- Footpath pour underway.
September 2024:
- Kerb and channel installation currently underway.
August 2024:
- Early bulk earthworks have concluded with drainage service construction underway.
July 2024:
- Bulk earthworks are underway with early service works planned for late July.