Stage 3A

2024-07-15

If you have any queries regarding your block at Wedge Rd, we recommend speaking with your conveyancer in the first instance. If you would like to reach out to us, please contact us on 0473 630 484 or email us at hello@wedgerd.com.au

February 2025:

  • Construction is now complete and lots are now Titled.

November 2024:

  • We continue to work through authority inspections and final compliance.
  • Title forecast: Q1 2025.

October 2024:

  • Construction works are now complete.
  • We continue to work through authority inspections and final compliance.
  • Title forecast: Q1 2025.

September 2024:

  • Authority compliance inspections are underway.
  • Title forecast: Q1 2025.

August 2024:

  • Overhead powerline removal has been completed with final excavation works commencing.
  • Final preparations are underway in anticipation of authority compliance inspections.

July 2024:

  • All services are completed with final works commencing lot trimming
  • Works to remove electrical infrastructure are planned for early August.