Construction Updates

17/07/2024

Stage 3

Wedge Rd. Skye construction continues to progress.

Titles are forecast for Q1 2025*.

If you have any queries regarding your block at Wedge Rd, we recommend speaking with your conveyancer in the first instance. If you would like to reach out to us, please contact us on 0473 630 484 or email us at hello@wedgerd.com.au

October 2024:

  • Electrical & communications install underway, nearing completion.
  • Footpath pour underway.

September 2024:

  • Kerb and channel installation currently underway.

August 2024:

  • Early bulk earthworks have concluded with drainage service construction underway.

July 2024:

  • Bulk earthworks are underway with early service works planned for late July.